PROJECT TITLE:

Cascadilla Gorge West Trail Wall Repairs

DESCRIPTION OF PROJECT:

1. Repair of existing gorge trail wall including but not limited to the following;
a. Continuous concrete foundation construction with form liner surface.
b. Subsurface trail and vertical drainage installation.
c. Masonry repair, remediation, and new construction.
d. Trail surface repair and placement as required.

ESTIMATED CONSTRUCTION BUDGET:

$65,000-$70,000

PRE-BID MEETING:

THIS IS A MANDATORY MEETING FOR ALL
09/29/2021 at 11:00 AM
via Zoom Meeting and Room 133 in Humphreys Service Building

BID OPENING:

10/19/2021 at 3:00 PM
NA - (Electronic Bid - Results will be posted to this website)

PROJECT SCHEDULE:

Start:
Within seven (7) days of written authorization to proceed.
Completion:
December 20, 2021

ARCHITECT/ENGINEER:

Matthew McKee     
John P. Stopen Engineering, LLP     
450 South Salina Street     
Syracuse, New York 13201      
Phone: 315-472-5238     
Email: mmckee@jpsllp.com

INVITED BIDDERS:

Alliance Masonry Corporation
Casler Masonry, Inc.
Cayuga Landscape Company, Inc.
C.P. Ward, Inc.
Lupini Construction, Inc.
Raymond E. Kelley, Inc.
Welliver McGuire, Inc.
607-639-1655
315-253-8871
607-257-3000
585-889-8800
315-736-8397
315-568-0982
607-535-5400
607-639-1629
NA
607-257-5242
585-889-6008
315-736-8809
315-568-0983
607-535-9254

To obtain documents Click Here